Sustainability Committee Meeting Report 8-13-13
4pm
Committee Members Present: Mike Lyon, Rob Bidner, Phil Mikus. Absent: Laura Coffee, Steve
Lawrence, Tom Rohrer.
Also: Woody Woodruff, Russ Alwood, Margie Henry
1. Community Clean Up Day
a. Tentative date selected: June 21, 2013
b. Tentative site: CMU lot 63/64
c. Tentative Materials to collect: Tires, Rubbish/Trash, Metals
d. Tentative hours: 8am to 1pm
e. Committees to be formed and defined
e.i. Layout
e.ii. Insurance
e.iii. Safety
e.iv. Promotion/Advertising/Resource Info
e.v. Bidding
e.vi. Volunteers
e.vii. Refreshments
Committees will be defined and assigned; time line will be finalized at the September 17th
meeting.
Tentative Time Line: (some tasks are Manager/Staff function, others committee volunteers)
Sept 17 – define and assign committees, finalize timeline
Oct - Finalize agreement with University, establish budget including printing/mailing
Nov -
Dec -
Jan – complete tire grant application
Feb – submit tire grant application
Mar – Issue RFP s; design promotion materials
Apr – review bids and select vendors
May – volunteer meeting
June – bake the cookies and hold the event
2. SkyStream Wind Generator – it was learned this week that XZERES Company has purchased the
Sky Stream Line. A phone call and email was made to Therese Unholtz, Customer Service
Manager for XZERES, 9025 SW Hillman Ct #3126 Wilsonville, OR 97070
(877) 404-9438. Committee recommends the Township move to wait to hear back from XZERES
before a decision is made on the next step regarding repair/sale/other.
Meeting adjourned at 5:05pm
Submitted by Phil Mikus, committee chair.